The building erection required extensive coordination and planning as the massive trusses - as long as 58 metres and weighing 44 tons each - were assembled using five 500-ton cranes. Bird's ability to assess and analyze the multifaceted logistics helped to boost productivity and subsequently yield a shortened production schedule.