Kings County Academy

The structural steel frame construction with a masonry and glazed curtain wall exterior features a geothermal heating system to efficiently heat the building. Although the team experienced major revisions to the electrical system during construction, Bird ensured work continued throughout the decision-making process. The team was determined to have the school ready for the upcoming school year.

Client
DEPARTMENT OF TRANSPORTATION & INFRASTRUCTURE RENEWAL
Consultant
FOWLER BAULD & MITCHELL
Contract Type
CONSTRUCTION MANAGEMENT
Project Size
80,000 SQ. FT.
Duration
20 MONTHS
Project Value
$15,000,000
Landscaping with Glazed Building Facade and Blue and Green Coloured Panels

As the project neared completion, functional performance testing was incorporated as part of the quality assurance program in order to resolve any issues prior to the third party inspection. In doing so, Bird was able to quickly hand over the academy following inspections.