During construction, Bird encountered a challenge when the building’s structure was near completion and a change in the scope of work was required - the elevator shaft originally terminating at the fourth floor was extended to the mechanical penthouse. Working with the design team, Bird made modifications by using high early strength concrete to mitigate the impact and allow the project to meet its original schedule.